CNC Active Library
ENTSO-E, for reasons of transparency, has been monitoring the implementation process in the European countries reporting all the necessary and publicly available information. This is an ongoing activity until Maybe 2018 for RfG NC and until September for DCC and HVDC NC. Available information, documents, websites, contacts can be found below.
In addition, a monitoring file (please check the Monitoring box on the left) can be downloaded which summarizes all the proposals for non-exhaustive requirements for all Connection Network Codes and their status for all the countries under the scope.
Choose a country in order to track the progress of Connection Network Code implementation.
Please, see below the implementation maps
Countries
DCC
DCC-Anforderungs-VO - National regulation of non-exhaustive DCC requirements
DownloadTOR Netze und Lasten mit Übertragungsnetzanschluss - National Grid Code for DCC
DownloadRFG
RfG-Anforderungs-VO - National regulation of non-exhaustive RfG requirements
DownloadRfG-Schwellenwert-VO - National regulation of A/B/C/D thresholds
DownloadTOR Erzeuger Type A, B, C, D - National grid code for Type A,B,C,D
DownloadDCC
Proposal for general requirements for Demand Connection (DCC)
DownloadRFG
Proposal for general requirements for grid connection of generators (RfG)
DownloadHVDC
Proposal for general requirements for grid connection of high-voltage direct-current systems and direct current-connected power park modules (HVDC)
DownloadDCC
RFG
HVDC
DCC
Decision of approval of non-exhaustive requirements for demand connection
DownloadNon exhaustive requirements for Demand Connection
DownloadRFG
Decision of approval of national maximum power thresholds for type A, B, C and D of power park modules and non-exhaustive requirements of all types of production modules
DownloadNational maximum power thresholds for type A, B, C and D of power park modules
DownloadNon-exhaustive requirements of all types of production modules
DownloadHVDC
Decision of establishing non-exhaustive requirements for high voltage direct current systems and direct current-connected power park modules
DownloadNon-exhaustive requirements for high voltage direct current systems and direct current-connected power park modules
DownloadDCC
Requirements laid down pursuant to EU regulation 2016/1388 – Demand Connection Code (DCC)
DownloadRFG
Requirements laid down under EU regulation 2016/631 – Requirements for grid connection of Generators (RfG)
DownloadHVDC
Requirements set under EU regulation 2016/1447: Requirements for grid connection of high voltage direct current systems and direct current-connected power park modules (HVDC), articles 11-54
DownloadDCC
Technical Connection Rules (TCR) for Extra High Voltage Network (VDE-AR-N 4130) (EN, DE)
DownloadTechnical Connection Rules (TCR) for High Voltage Network (VDE-AR-N 4120) (EN, DE)
DownloadTechnical Connection Rules (TCR) for Medium Voltage Network (VDE-AR-N 4110) (EN, DE)
DownloadPower Generating Plants Connected to the Low-voltage Network (VDE-AR-N 4105) (EN, DE)
DownloadInterface TSOs & DSOs (VDE-AR-N 4141-1) (DE)
DownloadCascading Measures for the System Safety of Power Grids (VDE-AR-N 4140) (DE)
DownloadRFG
Technical Connection Rules (TCR) for Extra High Voltage Network (VDE-AR-N 4130) (EN, DE)
DownloadTechnical Connection Rules (TCR) for High Voltage Network (VDE-AR-N 4120) (EN, DE)
DownloadTechnical Connection Rules (TCR) for Medium Voltage Network (VDE-AR-N 4110) (EN, DE)
DownloadPower Generating Plants Connected to the Low-voltage Network (VDE-AR-N 4105) (EN, DE)
DownloadCollaboration of network operators during critical grid states (VDE-AR-N 4140) (DE)
DownloadHVDC
Technical Connection Rule (TCR) for the connection of HVDC systems and generation plants connected via HVDC systems (VDE-AR-N 4131) (EN, DE)
DownloadDCC
Decision RAE 1166/2020 (Official Gazette of the Hellenic Republic B’ 3698 of 03.09.2020)
DownloadRFG
Decision RAE 1165/2020 (Official Gazette of the Hellenic Republic B’ 3757 of 07.09.2020).
DownloadHVDC
Decision RAE 1167/2020 (Official Gazette of the Hellenic Republic B’ 3762 of 07.09.2020).
DownloadDCC
EirGrid's proposal for the general application of technical requirements in accordance with Articles 12-21 and Articles 27-30 of the Commission Regulation (EU) 2016/1388 establishing a Network Code on Demand Connection
DownloadRFG
Proposal for generaal application of technical requirements in accordance with Articles 13-28 of the Commission Regulation (EU) 2016/631 establishing a network code on requirements for grid connection of generators
DownloadHVDC
Not yet implemented
DownloadDCC
RFG
HVDC
DCC
RFG
HVDC
DCC
RFG
HVDC
DCC
NC DC Requirements for general application PL & ENG versions + NRA approval
DownloadRFG
NC RfG Requirements for general application PL & ENG versions + NRA approval
DownloadNC RfG Maximum capacity thresholds NRA approval
DownloadHVDC
NC HVDC Requirements for general application PL & ENG versions + NRA approval
DownloadRFG
Order no. 72 of 02.08.2017 approving the technical norm on the technical requirements to connect synchronous power-generating modules to public electrical grids -
DownloadOrder no. 214 of 19.12.2018 amending and supplementing Order no. 72/2017 of the President of the National Energy Regulatory Authority approving the technical norm on the technical requirements to connect synchronous power-generating modules to public electrical grids -
DownloadOrder no. 208 of 14.12.2018 approving the technical norm on the technical requirements to connect power-generating modules, power plants modules and offshore power park modules to public electrical grids -
Download