Iberian Peninsula Blackout28 April 2025
Disclaimer
The documents and materials published on this web page by ENTSO-E are considered working documents and are provided for general informational purposes only. These documents are based on the most current information available to ENTSO-E at the time of publication. Thus, the information contained herein may be updated, modified, or replaced as new data becomes available or circumstances change.
ENTSO-E makes no representations or warranties, express or implied, as to the completeness, accuracy, reliability, or suitability of the information contained in these documents. Users are encouraged to verify the information independently and consult directly with ENTSO-E for the most recent and authoritative updates.
By using this web page, you acknowledge and accept that the content may be revised at any time without prior notice, and ENTSO-E shall not be held liable for any loss or damage arising from the use or reliance on the information provided.
Introduction
On 28 April 2025, at 12:33 CET, the power systems of Spain and Portugal experienced a blackout. A small area in France, close to the border with Spain, was also affected for a limited duration.
This page provides consolidated information on the incident, including the affected areas, a preliminary sequence of events, the restoration process, and details about the Expert Panel established to investigate the causes. Further updates will be provided as the investigation progresses.
Affected Area
The blackout impacted the entire Iberian Peninsula, encompassing both Spain and Portugal. Additionally, in France, a small area near the Spanish border experienced disruptions for a limited duration, and several industrial consumers and generators were affected, more notably a nuclear power unit that tripped around the same time as the incident in the Iberian Peninsula. The remainder of the power system of Continental Europe did not experience any significant disturbance.
Figure 1 – Geographic area affected by the incident of 28 April 2025.
Preliminary Chronology of Events
All information published to date, including the present communication, is based on the preliminary findings by the Expert Panel and may change at any time. The investigation follows the legal framework under the European Union Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (SO GL).
A preliminary chronology based on the information known so far has been identified regarding the complex sequence of events which have occurred prior to the blackout. The final description of the sequence of events will be established by the Expert Panel in a factual report, followed by the in-depth analysis and recommendations in the final report which will be published.
Preliminary findings indicate that during the half hour preceding the blackout, two periods of oscillations (power and frequency swings) were observed in the Continental Europe Synchronous Area (CE SA).
The first one took place from 12:03 to 12:07 CET. Preliminary analysis of the available information indicates that this was a local oscillation, primarily affecting the Spanish and Portuguese power systems.
The second oscillation started at 12:16 CET to 12:22 CET. This was an inter-area oscillation corresponding to the well-known East-West Continental mode. It was effectively mitigated through countertrading measures, which reduced power flows between France and Spain, also with a switch from AC emulation to fixed power in the operation mode of the HVDC link and the coupling of the internal power lines in the South of Spain.
Following the second oscillation, the voltage was within the range of 390–420 kV, before increasing again, but still within the operational voltage range in the transmission network. At that moment, Spain’s international scheduled exchanges – all in the export direction – were 1,000 MW to France, 2,000 MW to Portugal and 800 MW to Morocco.
The currently available data indicates the following sequence of events during the incident:
generation trips were observed in the South of Spain, accounting to an initially estimated total of 2200 MW. No generation trips were observed in Portugal and France within this timeframe. As a result of these events a voltage increase was observed in Spain, leading to a similar increase consequently also in Portugal, and the frequency decreased.
the voltage of the South area of Spain increased sharply, and consequently also in Portugal. The over-voltage triggered a cascade of generation losses that caused the frequency of the Iberian Peninsula power system to drop.
the Iberian Peninsula started to lose synchronism with the European System.
the automatic load shedding and System Defence Plans of Spain and Portugal, elaborated in accordance with legal obligations under SO GL, were activated but were unable to prevent the collapse of the Iberian power system.
the AC overhead lines between France and Spain were disconnected by protection devices against loss of synchronism.
all system parameters of the Spanish and Portuguese electricity systems collapsed, and the HVDC lines between France and Spain stopped transmitting power.
Restoration Process
Following the incident, each impacted Transmission System Operator (TSO) immediately activated the respective system restoration plans, elaborated in accordance with Commission Regulation (EU) 2017/2196 establishing a network code on electricity emergency and restoration (NC ER), as well as any other relevant procedures and protocols for restoring the voltage of the electricity system.
Power system restoration in some regions of the Iberian Peninsula was facilitated, among others, by the activation of the power system resources such as black-start processes in certain power plants, as well as by the existing interconnections with France and Morocco.
The rapid restoration of supply in Spain and Portugal demonstrated the preparedness and efficiency of the affected TSOs, Red Eléctrica and REN with the support and collaboration of the French TSO RTE, as well as the Moroccan utility ONEE. This was possible by the joint work and cooperation of TSOs developed over the years, both between the control centres and within ENTSO-E. In addition, the real-time monitoring and coordination of the status of the European electricity systems was achieved by the European Awareness System platform, a tool developed by all TSOs within ENTSO-E.
The main steps undertaken by the TSOs for the restoration process were as follows:
REN requested black-start mode start-ups for the Castelo de Bode hydropower plant and the Tapada do Outeiro combined cycle gas turbine power plant, respectively.
a first 400 kV line between France and Spain was re-energised (Western part of the border).
the hydropower plant of Castelo do Bode, operating in black-start mode, connected to the 220 kV of the neighbouring REN substation.
the interconnection between Morocco and Spain was re-energised.
several hydropower plants in Spain with black-start capability launched their black-start processes to initiate the restoration of the system.
the Eastern part of the France-Spain interconnection was re-energised.
REN had established two restoration islands and was progressing and rapidly restoring the supply of demand in these regions, using the Castelo do Bode hydropower plant and the Tapada do Outeiro combined cycle gas turbine power plant.
the first 220 kV tie-line between Spain and Portugal was re-energised, allowing to speed up the restoration of the Portuguese system.
the Southern 400 kV tie-line between Spain and Portugal was re-energised.
the restoration process of the transmission grid was completed in Portugal.
the restoration process of the transmission grid was completed in Spain.
Expert Panel
Following the blackout incident, on 12 May 2025, ENTSO-E set up a joint Expert Panel in line with Art. 15(5) of the Regulation (EU) 2017/1485 of 2 August 2017, establishing a guideline on electricity transmission system operation (SO GL) and the Incident Incident Classification Scale (ICS) methodology. The ICS Methodology is the framework for reporting and classifying incidents in the power system and for organising the investigation of such incidents, and is especially relevant to the work of the Expert Panel.
In line with the legal requirements of both SO GL and the ICS Methodology, when the incident is classified according to the ICS Methodology criteria as scale 3 incident – blackout – the Expert Panel is tasked to investigate the root causes of the incident, produce a comprehensive analysis, and make recommendations in a final report which will be published.
The Expert Panel consists of representatives from TSOs, the Agency for the Cooperation of Energy Regulators (ACER), National Regulatory Authorities (NRAs), and Regional Coordination Centres (RCCs).
The Panel is led by experts from TSOs not directly affected by the incident and includes experts from both affected and non-affected TSOs. The Expert Panel is led by Klaus Kaschnitz (APG, Austria) and Richard Balog (MAVIR, Hungary).
ENTSO-E Bodies Convenors participating in the Expert Panel
- Olivier Arrivé – as chair of the System Operation Committee
- Robert Koch – as convenor of the Steering Group Resilient Operation
- Albino Marques – as convenor of the Regional Group Continental Europe
Experts from TSOs and RCCs participating in the Expert Panel
TSO/RCC | Expert |
---|---|
Amprion (Germany) | Tilman Ringelband |
EirGrid (Ireland) | Donna Kearney |
Energinet (Denmark) | Bent Myllerup |
PSE (Poland) | Rafal Kuczynski |
Red Electrica (Spain) | David Alvira |
REN (Portugal) | Filipe Ribeiro |
RTE (France) | Laurent Rosseel |
SEleNe CC (Greece) | Maria-Faidra Katsiantoni |
Swissgrid (Switzerland) | Bastien Grand |
Terna (Italy) | Giorgio Giannuzzi |
Experts from ACER and NRAs participating in the Expert Panel
ACER/NRA | Expert |
---|---|
ACER | Georgios Antonopoulos |
ACER | Uros Gabrijel |
ACER | Aleksander Glapiak |
ACER | Maria Barroso Gomes |
ACER | Domen Kodric |
ACER | Zoran Vujasinovic |
ANRE (Romania) | Alina Poanta |
ARERA (Italy) | Expert |
ARERA (Italy) | Expert |
BNetzA (Germany) | Jochen Gerlach |
BNetzA (Germany) | Thomas Hoelzer |
BNetzA (Germany) | Nicolas Krieger |
CNMC (Spain) | Virginia Garcia Escoin |
CNMC (Spain) | Teresa Ibanez Tarrago |
CNMC (Spain) | Diego Roldan Cabanillas |
CRE (France) | Martin Frédéric |
CRE (France) | Pierrick Muller |
CRE (France) | Sara Rami |
CREG (Belgium) | Marijn Maenhoudt |
EI (Sweden) | Expert |
ElCom (Switzerland) | Raffaele Bornatico |
ERSE (Portugal) | Jose Capelo |
ERSE (Portugal) | Paulo Oliveira |
ERU (Czech Republic) | Pavel Simoncik |
MEKH (Hungary) | Erika Szirmai |
URE (Poland) | Lukasz Makos |
URE (Poland) | Piotr Rak |
URE (Poland) | Witold Zuchowski |
Investigation
On 12 May 2025, the Expert Panel initiated its investigation into the causes of the blackout. The investigation is conducted in two phases:
- Data Collection and Analysis: The Panel will collect and analyse all available data on the incident to reconstruct the events of 28 April and determine the causes of the blackout.
For the data collection task, the Expert Panel has been receiving information from all affected TSOs. In addition, to facilitate the provision of third-party data to the Expert Panel, two letters were sent – one to Red Eléctrica and the other one by ENTSO-E to Spanish authorities. Both letters are available on this webpage. - Recommendations: Based on the findings, the Panel will establish recommendations to help prevent similar incidents in the future. These will be published in a final report and presented to the European Commission and Member States via the Electricity Coordination Group.
Based on the data collected so far, it appears that two of the main questions that the investigation will seek to answer are why the first generation units disconnected from the system, and why the System Defence Plans were unable to halt the process that led to the full blackout of the Iberian Peninsula.
Expert Panel meetings
- 12 May 2025
- 3 June 2025
- 23 June 2025
- 15 July 2025
FAQ
A Frequently Asked Questions (FAQ) section is being drafted separately and will be added to this page once finalised.
Publications & documents
- Press release: Incident in the power systems of Spain and Portugal
- Press release: Iberian Black-out: ENTSO-E congratulates Red Electrica and REN for the rapid recovery of the electricity systems of Portugal and Spain, and establishes an Expert Panel to investigate the incident
- Press release: ENTSO-E expert panel initiates the investigation into the causes of Iberian blackout
- Letter to MITECO - Data Collection for the investigation of the 28 April 2025 Iberian Blackout by the Expert Panel
- Letter to Red Eléctrica – Request for Data supporting the work of the Expert Panel for the 28 April 2025 Iberian Blackout
Contacts
- For any further information, please contact info@entsoe.eu
- For media requests, please contact media@entsoe.eu